Groundworks

Project: Ensleigh Primary School

Contractor: Rydon

Package value: £ 400 k

Date: 2017

Brief: Complete substructures, drainage, floor slabs, structural topping, insulation and screed package. External works package to provide a new Primary School facility for the new residential development at Lansdown on the outskirts of Bath.

————————————————————————————————————————————————-

Project: Bath College Radstock

Contractor: Midas Construction

Package value: £ 400 k

Date: 2017

Brief: Complete substructures, drainage, powerfloated concrete floor slabs and external works package to provide a new college facility in Bath.

Top of page

————————————————————————————————————————————————-

Project: Great Western Academy Swindon

Main contractor: BAM Construction

Package value: £ 2 m

Date: 2017

Brief: 30,000m3 Bulk Earthworks with a cut/fill balance to eliminate waste off site.  Pile Caps & Ground Beams to the substructures.  Structural floor toppings using self-compacting concrete to the upper floors and insulated screed to the ground floors. Complete drainage system including SUDS car park and external works package.  All to provide a new secondary school facility for Swindon near to the Tadpole development.

————————————————————————————————————————————————-

Project: Brynmenyn School

Main contractor: BAM Construction

Package value: £ 1.8 m

Date: 2017

Brief: 20,000m3 Bulk Earthworks with a cut/fill balance to eliminate waste off site.  Pads and strip footings to the substructures.  Complete drainage system including SUDS car park and external works package.  Sports pitch constructed using site-won topsoil.  All to provide a new primary school facility in Bridgend.

Top of page

————————————————————————————————————————————————-

Project: Caradog house

Main Contractor: Midas Construction

Value: £ 600 k

Date: 2017

Brief: Alterations and reconfiguration of existing drainage systems within an existing building to accommodate the change of use from office space to student accommodation.  Installation of a 6m deep x 4m dia. chamber for a pumping station at basement level.  New pile caps and ground beams for an extension to the existing building.

————————————————————————————————————————————————-

Project: Pencoed School

Main Contractor: BAM Construction

Value: £ 2 m

Date: 2017

Brief: 18,000m3 of Bulk Earthworks and disposal off site.  Pads and strip footings to the substructures.  New access road and car park.  Complete drainage system including attenuation tank and external works package.  All to provide a new primary school facility in Pencoed, Bridgend.

————————————————————————————————————————————————-

Project: The Deanery, Swindon

Main Contractor: BAM Construction

Value: £ 1.8 m

Date: 2017

Brief: 15,000m3 of Bulk Earthworks with lime stabilisation to improve the bearing capacity of the clay.  Building substructures comprising Pile Caps & Ground Beams.

————————————————————————————————————————————————-

Top of page

Screeding

Project: Queens Building, Bristol University

Main Contractor: Willmott Dixon Construction

Value: £ 70 k

Date: 2011/2017

Brief: Insulation, acoustic layer, Screed, Lytag Concrete and resin as part of a new build extension and refurbishment for Bristol University.

————————————————————————————————————————————————-

Project: Duffryn High School, Newport

Main Contractor: BAM Construction

Value: £ 200 k

Date: 2017

Brief: 7500m2 Self-levelling screed to new build blocks over 3 floors, together with 330m2 of cementitious flowing screed and sundry sand & cement screed.

————————————————————————————————————————————————-

Underfloor heating